MA & UD Department–Madanapalle Water Supply
Improvement Scheme with Handri Niva Sujala Sravanthi Canal as source – Administrative Sanction for Rs. 138.00
Crores Accorded – Orders Issued.
x-x-x-x-x-x-x-x-x-x-x-x-x-x-x-x-x-x-x-x-x-x-x-x-x-x-x-x-x-x-x-x-x-x-x-x-x-x-x-x-x-x-x-x-x-
MUNICIPAL ADMINISTRATION & URBAN DEVELOPMENT(A1)
DEPARTMENT.
G. O. Ms. No. 670
Dated: 13.07.2005.
Read the Following:-
1) G. O. Ms. No. 45, Municipal
Administration and Urban Development (A2)
Department, dated 19.02.2004.
2) From
the Engineer-in-Chief (Public Health), Hyderabad Letter No./T4/
MDP/2005,
dated 12.07.2005.
----:: 00
::----
ORDER:
In the reference 1st read above Government
have accorded administrative sanction for Madanapalle Water Supply
Improvement Scheme with Summer Storage Tank across Bahuda River at Chippili
Village at a cost of Rs. 1054.70 Lakhs.
2. The Engineer-in-Chief (Public Health), Hyderabad in his
letter 2nd read above has reported that the I & CAD Department
has furnished Hydrological Surveys / Rainfall
particulars for the past 40 years which revealed that once in 2 years
the rainfall is very meager. The storage
proposed is 55.6 Mcft only and after deducting evaporation and percolation
losses, the water will be sufficient for 70 days only. Therefore the scheme cannot be formulated in absence of a dependable
source for the entire year.
3. The Engineer-in-Chief (Public Health),
Hyderabad has further informed that in a meeting held with Principal Secretary,
Irrigation, Secretary (MA & UD) and Engineer-in-Chief (PH), Hyderabad it
was suggested to have a water supply scheme with Handri
Niva Sujala Sravanthi Canal as source
which is passing nearby Madanapalle instead of a source from the Bahuda River at Chippili village. Accordingly the matter has been examined in
consultation with Irrigation Department and Engineer-in-Chief (Public Health),
Hyderabad prepared a preliminary
proposal costing Rs. 138.00 Crores with
90% HUDCO assistance for providing water supply scheme with Summer Storage Tank
and other connected works with the
source from Handri Niva Sujala
Sravanthi Canal. He has requested the Government
to accord administrative sanction for Rs. 138.00 Crores.
4. The Government after careful
examination hereby accord administrative sanction, in super session of the
orders issued in G.O. 1st
read above, for Madanapally
Water Supply Improvement Scheme with Summer Storage tank and other connected
works with Handri Niva Sujala Sravanthi Canal as source at a total cost of Rs.
138.00 Crores with the following
financing pattern:
HUDCO (90%) .. Rs,
124.20 Crores.
Municipal
Contribution (10%) Rs., 13.80 Crores
-----------------------
Total
Rs. 138.00 Crores
-----------------------
5. The above sanction is subject to the
council resolution from Madanapalle
Municipality approving the above method
of financing.
P.T.O.
----:: 2 ::----
6. The Engineer-in-Chief (Public Health),
Hyderabad is directed not to commit any expenditure on the above scheme till the source of water through Handri Niva Sujala Sravathi Canal
is fully established by Irrigation Department.
7. This order issues with the concurrence
of Finance (Exp. M&F) Department vide their U. O. No.
6065/344/A1/Exp.M&F/2005, dated 13.07.2005.
(BY
ORDER AND IN THE NAME OF THE GOVERNOR OF ANDHRA PRADESH)
S.P. SINGH,
SECRETRY
TO GOVERNMENT.
To
The Engineer-in-Chief
(Public Health), Hyderabad.
The Commissioner &
Director of Municipal Administration, Andhra Pradesh, Hyderabad.
All the concerned through
the Engineer-in-Chief (Public Health), Hyderabad.
The Accountant General,
Andhra Pradesh, Hyderabad.
The District Treasury
Officer, Hyderabad,
Copy to: Finance (Exp. M&F) Department.
Special Secretary to C.M. with reference to the CMP
No. 719/CMP/2005, dated
19.01.2005.
P.S. ro M(MA
& UD).
SF/SC.
// FORWARDED
BY ORDER //
SECTION
OFFICER.