ABSTRACT.
Andhra Pradesh Urban Local
Bodies Infrastructure Development Project (City Challenge Fund) – Grounding of
works – 3rd Party Quality Control – Entrustment of the work to the
consultant firms – Orders – Issued.
x-x-x-x-x-x-x-x-x-x-x-x-x-x-x-x-xx-x-x-x-x-x-x-x-x-x-x-x-x-x-x-x-x-x-x-x-x-x-x-x-x-x-x-x-x-x-
MUNICIPAL
ADMINISTRATION & URBAN DEVELOPMENT (A1) DEPARTMENT
G. O. Ms. No. 4. Dated \: 03-01-2004.
Read the following:-
1) G. O.
Ms. No. 483, M.A. dated 21.10.2003.
2) G. O.
Ms. No. 487, M.A. dated 23.10.2003.
3)
Government Memo No. 20273/A1/2003-2, M.A. dated 05.12.2003.
4) From
the Engineer-in-Chief (PH), Hyderabad Letter No. 487/T6/
APULBIDP/QC/2003, dated 18.12.2003.
5) Government Memo No.
23755/A1/2003-1, M.A. Dated 19.12.2003
6) From
the Engineer-in-Chief (PH), Hyderabad Letter No. 487/T6/
APULBIDP/QC/2004, dated 01.01.2004.
--:: 00 ::--
ORDER.
In the G.,O. 1st read above orders were issued
among other things, according administrative sanction to Andhra Pradesh Urban
Local Bodies Infrastructural Development Project (City Challenge Fund) with a
total cost of Rs. 300.00 Crores with HUDCO loan assistance covering 114
Municipalities for creation of infrastructure facilities like roads, drains,
water supply etc.
2. In the G. O. 2nd read above necessary guidelines
for implementation of project were also issued. In the said guidelines it was instructed to take up the works
with 3rd Party Quality Assurance.
3. In the Memo 3rd read above, the Engineer-in-Chief
(PH), Hyderabad has been permitted to negotiate with National Council for
Cement and Building Materials, Gatchi Bowli. Hyderabad, for 3rd
Party Inspection, on the terms and conditions followed in respect of irrigation
works.
4. The Engineer-in-Chief (PH), Hyderabad in his letter 4th
read above has reported that the proposed works have been identified,
administrative sanctions for individual works have been accorded and also
technical sanctions has been given by the P.H. Engineering Department and work
orders are being issued for grounding the works. He has stated that as the NCCBM. Gatchi Bowli, Hyderabad did not turn up, specific offers with full
details have been called for from some other consultant firms.
5. In his letter 6th read above. the Engineer-in-Chief
(PH), Hyderabad has reported that with reference to the instructions in the
Government Memo dated 19.12.2003, the 3rd Party Quality Assurance
Agencies already short listed in APUSP
Project have been asked to submit their budgetary offer based on the TOR (Terms
of Reference) provided to the consultants on or before 27.12.2003 and that the
following firms have submitted their specific offers within the stipulated time
by furnishing the technical details with organograms, man power details, proven
experience, lab facilities etc. besides consultancy fee to be paid and terms of
payment.
P.T.O
--::2
::--
1) M/s KITCO LTD., Cochin.
2) M/s M.D.P. Consultants Ltd., New Delhi,
in association with
M/s. N.C..P.E.,
Hyderabad.
3) M/s. TUV Suddeutschland India Ltd.,
Hyderabad.
4) M/s. Willbur Smith Associates,
Hyderabad.
6. The Engineer-in-Chief (PH), Hyderabad has stated that an
evaluation committee has been constituted and based on the details of the
consultancy fees, service tax etc. quoted by the firms, it is preferred to
entrust the work of quality control inspection to two agencies i.e. the 2nd
and 4th firms, in view of the magnitude of work involved. He has requested the Government to issue
necessary orders in the matter.
7. The Government after careful consideration of the proposal
of the Engineer-in-Chief (PH), Hyderabad, hereby permit him to entrust the
3rd Party Quality Control Inspection job to the following two firms as per the Terms Of Reference at revised offers as agreed and with the jurisdiction, duly charging
the expenditure to the respective individual works.
1) M/s M.D.P.
Consultants Ltd., New Delhi Ananthapur,
Warangal and
in association
with M/s N.C.P.E.Hyderabad. Hyderabad
P. H. Circles.
2) M/s Willbur Smith Associates, Hyderabad Visakhapatnam,Rajahmundry
Guntur and Nellore P.H. Circles
8. The Engineer-in-Chief (PH), Hyderabad shall take necessary
action accordingly.
(BY
ORDER AND IN THE NAME OF THE GOVERNOR OF ANDHRA PRADESH)
S.R. RAO,
PRINCIPAL
SECRETARY TO GOVERNMENT.
To
The Engineer-in-Chief (PH), Hyderabad.
Copy to the Commissioner and Director of Municipal
Administration,
Andhra
Pradesh, Hyderabad.
Copy to the Managing Director, APUFIDC., Hyderabad.
SF/SC.
// FORWARDED
:: BY ORDER //
SECTION
OFFICER.